Road Conditions

16th June 2011 - All restrictions to be lifted.

SYD Road Limited Partnership gives notice that all load restrictions will be lifted at 0600am Saturday 18th June 2011 on the SYD Road.

Overweight axle loads are permitted subject to the Carrier entering into a Road Use Agreement with SYD Road Limited Partnership and obtaining all necessary MoT Permits.

Road Use Agreements are only issued for individual loads, no blanket agreements covering multiple loads are issued. Any questions regarding the SYD restriction can be directed to Gerry Anderson at (604) 699-2928

An explanation of legal axle loads is shown in the table below:

 

 

For information on other roads, please visit the MOT Load Restriction website

 

Road Repairs

Maintenance Programme - Spring/Summer 2011

SYD Road users are advised that routine maintenance activities will be carried out throughout late spring and summer 2011. These will consist of:

  • Bridge cleaning/ repair
  • Grading/ gravelling of road surface
  • Spot repair to road surface
  • Dust control
  • Brushing
  • Watercourse/ culvert maintenance

For further information on road bans, road repairs or any other issues, please contact Gerry Anderson at:

Office - (604) 699 2928

Cell - (604) 329 5500

email - gerry.anderson@ledcor.com

You may also use our toll free reporting line on:

Toll free: 1-866-4-LEDCOR (1-866-453-3267)